Community Crossing Two Week Schedule.
Wallace Construction will begin Patching on Tuesday August 12 on Main Street, Harrison Street, Washington Street and Maple Lane.
August 13 they will be patching on Northeast Avenue.
Sections of roads to be repaired.
Indianapolis Road from Samuel Moore Parkway to County Line Rd.
Northeast Street from Indianapolis Road to Bolton Avenue.
Harrison Street from Monroe Street to Indiana Street.
Main Street from Monroe Street to just west of Harrison Street.
Washington Street from Indiana Street to just east of Maple Lane.
Maple Lane from Bridge Street to St. Clair Street.
Cottonwood Drive from Cul-de-sac to Cul-de-sac.
Mainline Milling will begin on August 14 on Indianapolis Road.
August 15 they will be on Northeast Street, Maple Lane and Washington Street.
August 18 on Harrison Street, Main Street and Cottonwood Court.
Mainline Paving will begin on August 15 on Indianapolis Road. August 18 on Northeast Street, Maple Lane and Washington Street.
August 19 will be Harrison Street, Main Street and Cottonwood Court.
All dates are subject to change depending on weather and any unexpected delays.