Update! The weather has impacted the schedule. They will now proceed as follows. They will begin work March 18th with saw cutting and excavating on Brentwood Drive between Indianapolis Road and St. Clair Street. They will start pouring concrete on Tuesday March 19th. They hope to complete the concrete work on Brentwood Drive by March 31st. This, of course is weather permitting.